Monday, October 25, 2021

How to prepare a detailed construction estimate


When preparing a bid, estimators create a general framework with cost recovery in mind.  Estimators should therefore have knowledge of the technologies involved in building the project,  which allows them to divide projects into individual pieces of work, namely physical subcomponents, systems, etc  These work packages will naturally consume resources generating costs that must be recovered from the client.

What are the steps followed to develop the estimate?

A chart of cost accounts acts as a guide or checklist as the estimator reviews the plans and specifications to highlight which cost centres are present in the contract being estimated.

The estimator should generally follow certain steps in developing the estimate:

Break the project into cost centres.

Estimate the quantities required for most cost centres that represent physical end items which is commonly called quantity takeoff.  For those cost centres that relate to nonphysical items determine an appropriate parameter for cost calculation, namely, the level of builder’s risk insurance required by the contract or the amounts of the required bonds.

Price development for physical work items may require an analysis of the production rates to be achieved based on resource analysis.  The estimate should therefore:

Assume work team composition to include number of workers, skilled and unskilled, and equipment required.

Estimate an hourly production rate based on the technology being used.

Make an estimate of the efficiency to be achieved on this job, considering site conditions and other factors.

Calculate the effective unit price.

Calculate the total price for each cost centre by multiplying the required quantity by the unit price.  This multiplication is called an extension and this process is called running the extensions.


How to estimate construction costs

 The key to a successful project and effective cost control is the development of a good estimate as the basis for bid submittal.


The estimate serves as a “flight plan” that is followed by the project team and becomes an essential tool in achieving a profit. If the flight plan is unrealistic or contains basic errors the contractor will certainly lose money. However, if the estimate is strategically calculated and reflects the costs that will be encountered in the field, the chances of a profitable job are greatly increased.


Estimating is essentially the process of looking into the future and attempting to predict project costs and resource requirements.  A consistent procedure or set of steps is therefore needed for preparing an estimate to minimize errors and achieve reliable results.

Types of estimates

The estimating method depends on the level of design detail that is available.  Before the commencement of design only the conceptual information is available.  A comprehensive unit such as a square foot of floor space or a cubic foot of usable space is used to characterize the facility being constructed.  The representative unit is then multiplied by a price per unit to obtain a gross estimate of the facility cost.  This conceptual estimate becomes useful in the schematic or budgetary phase when design details are not available.  However, the figures developed are of a limited use as soon as design data are available.


Once design details are available the designer maintains estimates of costs to keep the client informed of the general level of costs to be expected.  The production of the plans and specifications proceeds in two steps.  The first step is called preliminary design and offers the owner a pause in which to review construction before detail commences.  This usually takes place at 40% completion of the total design and extends the concept documentation.  This preliminary estimate is prepared by the architect or architect/engineer to reflect expected costs based on more definitive data.


After the preliminary design is approved by the owner, final or detail design is accomplished.  The detail design form part of the plans and specifications that are given to the contractor for bidding purposes.  At this stage the architect or engineer will produce a final engineer’s estimate indicating the total job cost minus markup.


The owner’s estimate is used to ensure that the design produced is within the owner’s financial resources to construct and establish a reference point in evaluating the bids submitted by the competing contractors.


The bid estimate takes place when the contractor prepares his estimate of the job’s cost to include a markup for profit.  This bid as well as the engineer’s estimate require a greater level of effort and a considerable number of estimate hours to prepare.


As the project proceeds from concept through preliminary design to final design and the bidding phase, the level of detail increases, allowing the development of a more accurate estimate.


The Advantages of Choosing a Smaller Building Contractor for Your Project

Introduction When it comes to embarking on a construction project, one of the most crucial decisions you'll make is selecting the right ...